A) |
The use of the contingency reserves and submission of a change request to adjust the cost baseline |
|
B) |
The use of the contingency reserves without adjusting the cost baseline |
|
C) |
The use of the management reserves and submission of a change request to adjust the cost baseline |
|
D) |
The use of the management reserve without adjusting the cost baseline |
A) |
Defer the request until all of the stakeholders are in agreement |
|
B) |
Deny the request as the project sponsor has the final say |
|
C) |
Consult the project management plan |
|
D) |
Approve the request as the project manager has authority to decide for the group |
A) |
Project complexity |
|
B) |
Knowledge management |
|
C) |
Cost management plan |
|
D) |
Earned value management |